B1:-
1.External plastering in progress..
2.Seventh floor internal plastering completed.
3.Seventh floor plumbing and sanitary work completed.
4. Sixth floor flooring in progress.
5.Balcony railing work in progress.
6.External painting in progress.
7.Balcony railing painting in progress.
8.Seventh floor Primer and Putty work in progress.
B2:-
1.Seventh floor ceiling plastering in progress.
2.Sixth floor block work in progress.
3.Fourth floor internal plastering in progress.
4.Fourth floor plumbing and sanitary work in progress.
5.Third floor Primer and Putty work in progress.